1. A crisis alone is not enough
Pointing to a recognized crisis is not enough. Energy contracts typically use standardized language, drawn from the ICC Force Majeure Clause 2020 or the EFET General Agreement, requiring three things: the event was beyond the company’ s control, it was unforeseeable, and there was no reasonable way around it.
The unforeseeability test can be tough for state-owned operators to meet. For example, in ICC Case No. 12112( 2009), a state entity cited civil unrest in its own region to excuse non-performance to a joint venture with two European investors. The tribunal held the state to a higher standard of foresight than a foreign investor. But a pre-existing risk doesn’ t automatically defeat a claim. In Gujarat State Petroleum Corporation Limited and others v. Republic of Yemen( ICC Case No. 19299 / MCP, 2015), the tribunal asked whether there was a significant, sharp increase in risk beyond what was expected when the contract was signed. This issue cuts both ways in 2026: the longer the Hormuz conflict drags on, the harder it is to call each notice a fresh increase in risk. As heatwaves become almost annual, tribunals may start to ask whether these conditions are now the baseline.
The avoidability test is just as tough: was there a workaround? In ICC Case No. 1782 / 1973,
energy-oil-gas. com 17